BRE Watford, Science Park Building 17

Project Outline

The project involved clearing two floors of furniture in BRE’s building 17,
working closely with BRE Group to establish which items could be kept and
re worked into the new floorplans for 120 users. JPA worked with the BRE
Project Team and Feilden Clegg Bradley to finalise layouts and establish
requirements for new products to work alongside those identified as
suitable for re use, and integrate the two together seamlessly.

Client testimonial
“We’ve been working with JPA on the refurbishment and re furnishing of
BRE’s offices at their Watford campus. JPA’s approach is innovative and
pertinent of the times, prioritising the reuse, re-purposing and refurbishment
of furniture where possible along with new furniture provision and
manufacture to provide solutions that are not only sustainable but reduce
costs and add value.”

BRE Case Study 2
BRE Case Study 7
BRE Case Study 9
BRE Case Study 6
BRE Case Study 5
BRE Case Study (002)-1
BRE Case Study (002) p23 2
BRE Case Study (002) p22 1

Key Outcomes

  • Awarded BREEAM excellent
  • Awarded highly commended at the Bedfordshire and Hertfordshire
    Construction Excellence Awards
  • Completion of site audits and inventory by JPA prior to building
    clearance to identify products and materials suitable for re use in the
    new scheme
  • By recycling redundant furniture items BRE Group significantly improved
    their environmental performance by contributing to SDG15,
    Life on Land
  • 100% Carbon Neutral Installation by JPA Teams

Got a project? Call us today

Key Statistics

  • 240 items of existing furniture stock, re worked back into scheme
  • 7.44 tCO2e saved by not buying new furniture = 37 return economy flights between London and Edinburgh
  • £29,930 savings from re use
  • 22.68 tCO2e Landfill eliminated